Was on the front page of the enterprise
Navy museum work on hold
Broughton Construction won the $4,662,200 contract to build a new Patuxent River Naval Air Museum and Visitors Center last fall, but the project is now almost four months behind schedule.
St. Mary’s County government sent a stop-work order on Dec. 7, 2012, to Broughton Construction and last week sent another letter that could terminate the contract.
In order to guarantee that the work would be completed, Broughton Construction had to purchase performance bonds as required by the federal, state and local governments, which all contributed money to the 15-year-old museum project. The bonds the company purchased were fraudulent, according to county government officials.
SoMdNews.com: Navy museum work on hold